Steam header & boiler house insulation
1,850 running metres of steam header and boiler house pipework in rockwool with aluminium cladding, completed inside a nine-day plant shutdown.
Scope
1,850 running metres
Location
Dahej, Gujarat
20000+ projects executed since 1998, from single-line lagging to plant-wide shutdown scopes across Gujarat and western India.
Client names are withheld where the site is operational. Tell us the sector and the duty and we will point you at a comparable job — and, where the client permits, arrange a reference call.
1,850 running metres of steam header and boiler house pipework in rockwool with aluminium cladding, completed inside a nine-day plant shutdown.
Scope
1,850 running metres
Location
Dahej, Gujarat
Foil-faced glass wool fixed under a PEB roof, installed shift by shift without stopping the production line, bringing shop-floor temperature down measurably.
Scope
92,000 sq ft
Location
Morbi, Gujarat
Nitrile rubber with a continuous vapour barrier across 40 mm to 200 mm lines, plus panel-room detailing and insulated pipe supports.
Scope
40–200 mm lines
Location
Morbi, Gujarat
Density-graded rockwool with perforated GI lining and MLV barrier, measured at the boundary before and after handover.
Scope
Boundary noise within limits
Location
Ahmedabad, Gujarat
Duct wrap and closed-cell insulation with a fully sealed vapour barrier across AHU casings, chilled water headers and supply ducting.
Scope
AHU + chilled water
Location
Ahmedabad, Gujarat
Torch-applied APP membrane on the terrace with crystalline treatment to basement walls, detailed around penetrations and expansion joints.
Scope
Factory block
Location
Vatva GIDC, Ahmedabad
Ask for a reference on a scope like yours.
We are happy to arrange a call with a client running comparable duty, and to walk you through what we quoted and what we handed over.